UNDT/2010/197, Bowen

UNAT Held or UNDT Pronouncements

The early termination of his contract was not based on a proper or lawful evaluation of the Applicant’s performance. In the absence of a comprehensive and fair performance evaluation done at the time, the reasons given by the Respondent cannot be regarded as cogent or reliable because the Applicant did not have an opportunity to refute, answer or rebut them. They therefore represent just one side of the story and, however strongly felt by the Respondent, are not a reliable basis for a lawful termination of the contract before its expiry date. This is not a question of improper motivation. There is no evidence that the Respondent was motivated by anything other than a desire to have the project functioning efficiently. The Respondent’s failure was in not treating the Applicant in a fair and lawful manner in accordance with the Staff Rules and UNDP procedure. The Applicant had no legitimate expectation of his contract lasting more than the one year to which he agreed when he signed his offer of appointment. The Applicant did suffer harm as a consequence of the termination of his contract.

Decision Contested or Judgment Appealed

The Applicant has challenged the Secretary-General’s decision to terminate his employment on an appointment of limited duration with the United Nations Development Programme (UNDP) in March 2004. The termination was effected three months before the expiry of his contract on grounds of poor performance.

Legal Principle(s)

N/A

Outcome
Judgment entered for Applicant in full or in part
Outcome Extra Text

i. The Respondent’s decision to terminate the Applicant’s contract on 23 March 2004 is rescinded. ii. Payment to the Applicant of the salary and other entitlements he would have received until the end of his contract on 24 June 2004 less the payments in lieu of notice. iii. Payment of two years’ net-base salary at the rate which applied at the time of the termination of his contract. iv. Interest on the sums in orders ii and iii at 5.25 per cent, accruing from the date from 24 March 2004 to the date of this order. v. This Judgment shall be executed within 30 days of the expiry of the time provided for appeal. Failure to execute this Judgment within the stipulated period, will result in a further five (5) per cent of interest accruing on order iv above.

OAJ prepared this case law summary for informational purposes only. It is no official record and should not be relied upon as an authoritative interpretation of the Tribunals' rulings. For the authoritative texts, please refer to the judgment or order rendered by the respective Tribunal. The Tribunals are the only bodies competent to interpret their respective judgments, as provided under Article 12(3) of the UNDT Statute and Article 11(3) of the UNAT Statute. Any inaccuracies in the publication are the sole responsibility of OAJ, which should be contacted directly for any correction requests. To provide comments, don't hesitate to get in touch with OAJ at oaj@un.org.

The judgment summaries were generally prepared in English. They were translated into French and are being reviewed for accuracy of the translation.