Abuse of process before UNDT/UNAT
Administrative decision
Jurisdiction / receivability (UNDT or first instance)
Subject matter (ratione materiae)
The application was rejected and the Applicant was ordered to pay costs in the sum of USD 1,500 for abuse of process. On receivability: The absence of a response by the Office of Human Resources Management (OHRM), during a delay of ten working days between the Applicant鈥檚 request on 14 March 2014 to carry out an investigation and his request for management evaluation on 28 March 2014, could not reasonably and sensibly be considered as an implied unilateral decision. It could also not be construed as a failure to act promptly in accordance with ST/SGB/2008/5. There is no appealable...